How should you configure this task before updating the Work?Ī. Set Effort Driven to Yes, then input 30 hours Workī. Set Type to Fixed Duration, then input 30 hours WorkĬ. Set Type to Fixed Units, then input 30 hours Workĭ. Set Effort Driven to No, then input 30 hours Workĥ. Which 5 fields get copied when you save a Baseline?Ī. Name, Duration, Start, Finish, Resource Nameī. Duration, Start, Finish, % Complete, WorkĦ. You just updated the Duration of a task within the execution phase of your project and then noticed that the current Finish date of the project changed. There is no one else that can assist with this task. She just informed you that based upon some new found information, the task is really going to take 30 hours worth of Work to complete.

The original estimate of Work for this task was 20 hours. She is responsible for working on only one task next week. How should you configure this task before adding the second resource?Ī. Set Type to Fixed Duration, and Effort Driven to Yesī. Set Type to Fixed Units, and Effort Driven to YesĬ. Set Type to Fixed Work, and Effort Driven to Noĭ. Set Type to Fixed Work, and Effort Driven to YesĤ. You have a resource on your team who is only available 50% of the time. You have an additional resource on the team who could help with this task. Due to a change in a delivery date, you discover that you now need to complete this task in 3 days or less.

Which is the easiest way to do that?Ī. Choose >Tools, >Options, and uncheck the Show Summary Tasks optionĬ. Outdent all tasks and milestones and delete the Summary Tasksĭ. Choose >Project, >Group, >Group by tasksģ. You have a task that spans 5 days in Duration, has only one Resource assigned, and consists of 40 hours of planned Work. What is the easiest way to do that?Ī. Insert a Summary Task at the top of your schedule and indent all tasks below it.ī. Enable the Project Summary Task through >Tools, >OptionsĬ. Insert a task at the top of your schedule and establish the predecessors appropriately.ĭ. Enable the Project Summary Task through >Project, >Project InformationĢ. You would like to quickly see only the tasks and milestones within your project schedule (not the summary tasks). 1. You would like to add a row at the top of your project schedule that rolls up or sums all the information below.